Project Approval
......................................................................................................................................................................................
Date
Approval/Permit
Description
Agency
23 October 2015
PAT Report
Approval to change from Single Flash technology to Binary ORC technology
Department of Environment, Sabah
26 August 2015
Provisional Licence
Provisional Licence
Energy Commission
2 July 2015
FiAH Certificate
Feed-in Approval Holder Certificate
Sustainable Energy Development Authority
2 July 2015
REPPA (FiT)
Renewable Energy Power Purchase Agreement (REPPA)
Sabah Electricity Sdn. Bhd.
6 May 2015
Federal Government Gazette for Feed-in Tariff rate for geothermal energy
Confirmation of Feed-in Tariff rate for geothermal energy, gazetted under the Renewable Energy (Amendment of Schedule)(No.2) Order 2013
Federal Government
11 September 2014
Earthworks EIA
Approval for EIA Earthworks Report
Environmental Protection Department Sabah
4 September 2014
Earthworks EIA
Letter of Undertaking for EIA Report
Environmental Protection Department Sabah
10 July 2014
Earthworks EIA
Letter of Offer for Earthworks EIA Approval and Approval Conditions for EIA
Environmental Protection Department Sabah
26 December 2013
Federal Government Gazette for geothermal energy
Geothermal energy has been gazetted under the Renewable Energy Act 2011, as published in the Renewable Energy (Amendment of Schedule) (No.2) Order 2013
Federal Government
13 September 2013
ITA
Incentive Tax Allowance
Malaysian Investment Development Authority
5 September 2013
PAT Report
Preliminary Site Assessment Report
Department of Environment, Sabah
22 November 2012
CDM
Clean Development Mechanism. The project has been registered for CDM under the UNFCCC
United Nations Framework Convention on Climate Change
19 November 2012
OP
Occupation Permit for Power Plant Site
Sabah Forestry Department
17 August 2012
LLA
Land Lease Approval
Sabah Parks
25 May 2011
FFA
Facilitation Fund Agreement with Bank Pembangunan Malaysia for a grant of RM 35 million for the construction of access road
Public Private Partnership Unit, Prime Minister's Department
22 April 2011
SCORE
Approval from SCORE (Special Committee on Renewable Energy) to develop project under SREP (Small Renewable Energy Program)
Ministry of Energy, Green Technology & Water (KeTTHA)
Project Progess Activity
......................................................................................................................................................................................
Project
Progress
Description
Exploratory Drilling
Completed
  • Exploratory Drilling
  • Well testing
Civil and Structural Works
Completed
  • Access road to power plant site
  • Access road to Wellpad AK1
  • Access road to Wellpad AK2
  • Wellpad AK1 construction
  • Wellpad AK2 construction
  • Power plant site preparation
  • Logistic warehouse
  • Site office
Interconnection Facilities and Communication Facilities
Completed
  • Detailed Design
  • Transmission lines route survery from TMI to KLPG
Interconnection Facilities and Communication Facilities
In Progress
  • Transmission lines route survery from power plant to TMI-KLPG interconnection
Geoscience Survey
Completed
  • Geological survey
  • Geophysical survey
  • Geochemical survey
  • Geothermal conceptual model
Geoscience Survey
In Progress
  • Geophysical supplementary magneto-telluric survey
  • Stream conductivity survey
Project Development Progress
......................................................................................................................................................................................
Date
Progress
Description
Ongoing
Project Progress
Tawau Green Energy to set up Geothermal Resource Centre in Tawau. (MORE)
Ongoing
Project Progress
  • Construction of wellpad AK2 in progress
  • Drilling water supply system in progress
  • Detailed geological, geophysical and geochemical survey for northern flank of Mt. Maria in progress
  • Detailed MT data processing and interpretation in progress
Project Development
......................................................................................................................................................................................
Date
Progress
Description
2nd July 2015
FiT REPPA
FiT Renewable Energy Power Purchase Agreement between TGE & SESB for 21 years (MORE)
2nd July 2015
Feed-in approval certificate
SEDA issue Feed-in Approval Certificate (MORE)
May 2015
Project Progress
             Environmental Assessment to meet EPFI (Equator Principles Financial Institution)      
             Standards has commenced
December 2014
Project Progress
             Construction of wellpad AK2 commenced
October 2014
Project Progress
Access road (all weather gravel) from power plant site to wellpad AK2 completed.
30 September 2014
Project Progress
Construction of wellpad AK1 completed.
10 July 2014
EIA Approval
Approval of EIA Report from Environmental Protection Department Sabah, Malaysia.
May 2014
Project Progress
Access road (all weather gravel) from power plant site to wellpad AK1 completed.
April 2014
Project Progress
Detailed geological, geophysical and geochemical survey for eastern flank and western flank of Mt. Maria completed.
March 2014
Project Progress
Access road (all weather gravel) to power plant site completed.
28 March 2014
MoU Signing with UMS
Memorandum of Understanding with University Malaysia Sabah. (MORE)
MoU Signing with Atlas Copco
Memorandum of Understanding with Atlas Copco, USA. (MORE)
24 February 2014
MoU Signing with University of Auckland
Memorandum of Understanding with University of Auckland, New Zealand. (MORE)
30 January 2014
Announcement
TGE has recently appointed GeothermEx Inc. of the USA, a leading global geothermal specialist, to undertake works related to the resource assessment and confirmation of the Apas Kiri Geothermal Prospect. (MORE)
8 November 2013
Announcement
TGE has received confirmation from the Ministry of Energy, Green Technology and Water that: (MORE)
5 September 2013
PAT Report Approval
Approval of PAT Report from Department of Environment.
22 November 2012
Clean Development Mechanism
The project received final approval and registration with UNFCCC.
19 November 2012
Occupation Permit
Occupation permit for 50-year period was received from Sabah Forestry Department (SFD). This will enable TGE to conduct exploration surveys and later construct the power plant within the Mt. Andrassy Forest Reserve.
13 July 2012
FiT Approval
Subsequent to the site visit by SEDA delegation on 9 April 2012, SEDA (Sustainable Energy Development Authority) has agreed in principle that geothermal technology will be classified as one of the Renewable Energy technologies that qualify for Tariff Incentives (Feed-in Tariff, FiT) in accordance with the Renewable Energy Act of 2011. As such, TGE's geothermal power plant project will be eligible for the FiT rate.
20 August 2012
Clean Development Mechanism
Project was submitted to UNFCCC for final registration.
17 August 2012
Land Lease Agreement
TGE signed a 50-year Land Lease Agreement with Sabah Parks to enable it to conduct exploration surveys and later construct steamfield etc. in a portion of the Tawau Hills Park.
25 May 2012
TGE signs Facilitation Fund Agreement under PPP concept
TGE and the Public-Private Partnership Unit of the Prime Minister's Department on 25 May 2012 signed the Facilitation Fund Agreement for the Federal Government providing a RM35 million grant to TGE to help fund construction costs of preliminary infrastructure. (MORE)
2 March 2012
Clean Development Mechanism
The Project Design Document(PDD) for the project was posted on the UNFCCC Website.
1 December 2011
Clean Development Mechanism
Prior Consideration Form for project accepted by UNFCCC (United Nations Framework Convention on Climate Change).
9 August 2011
Clean Development Mechanism
Emissions Reduction Purchase Agreement (ERPA)
TGE signed the ERPA with a reputed Certified Emission Reductions (CER) offtaker on 9 August 2011. With the signing of the ERPA, TGE now has a buyer commited to offtake all of the available CERs from the project.
20 July 2011
Clean Development Mechanism
Stakeholders' Meeting
As required under the Clean Development Mechanism (CDM) protocol, TGE conducted a Stakeholders' Meeting at Kg. Tass, Andrassy, Tawau on 20 July 2011. Almost 200 participants, comprising  local residents, government officials, NGOs and representatives from local electronic and print media attended the meeting. Much positive feedback was received from participants, enabling TGE to proceed to registering the project with UNFCCC.
21 April 2011
SCORE Approval
At a meeting on 21 April 2011, the Special Committee On Renewable Energy (SCORE), under the Ministry of Energy, Green Technology and Water, approved TGE's application for the project to be categorized under the Small Renewable Energy Programme (SREP). The approval allows TGE to now commence negotiations with SESB for the Renewable Energy Power Purchase Agreement (REPPA).